hardQ. No. 16854-solve-this-time-and-work-question-isha-can-finish-a-project-in-20-days-and-naina-in-30-days-after

Solve this Time and Work question: Isha can finish a project in 20 days and Naina in 30 days. After working together for 5 days, Isha leaves. How many additional days will Naina require?

Last Updated:

This bilingual Time and Work item asks the learner to solve “Solve this Time and Work question: Isha can finish a project in 20 days and Naina in 30 days. After working together for 5 days, Isha leaves. How many additional days will Naina require?” through a complete, auditable work-rate equation. The validated answer is 17.5 days. The explanation preserves the original question-specific working, reconstructs the governing rule, checks every relevant condition or transition, and compares all three distractors. It builds disciplined reasoning, accurate option elimination and exam-ready verification for SSC, Railway, Banking, Defence, State examinations and other competitive tests.

A18.5 days
B19.5 days
C17.5 days
D16.5 days
Correct Answer: 17.5 daysYour Answer: C

Explanation

The verified answer to “Solve this Time and Work question: Isha can finish a project in 20 days and Naina in 30 days. After working together for 5 days, Isha leaves. How many additional days will Naina require?” is 17.5 days, option C. The question-specific working supplied with the item states: rk in 5 days = 5(1/20+1/30). The remaining work is divided by Naina's rate 1/30, giving 17.5 days.19.5 दिन This working identifies the relevant work-rate equation and connects the given information to the required result. After applying the verified rule, the required value or position is 17.5 days. The alternatives 18.5 days, 19.5 days and 16.5 days fail because each breaks at least one stated condition, transition, direction or arithmetic step. A plausible-looking option is not sufficient unless it reproduces the complete work-rate equation. This full replay leads only to 17.5 days, so option C is uniquely correct. The method is transparent, question-specific and suitable for SSC, Railway, Banking, Defence, State and other competitive examinations.

Important Notes

  • Rebuild the complete Time and Work work-rate equation before selecting 17.5 days.
  • Question-specific Time and Work working connects the stated clues or terms directly with 17.5 days.
  • Options 18.5 days, 19.5 days, 16.5 days each break a condition or transition in this Time and Work item.
  • Replay every step in the Time and Work work-rate equation to independently confirm 17.5 days.

Related Questions

View All

Test your Time and Work knowledge

Start Topic Test

FAQ

Time and Work FAQs

Common questions and clear answers for this topic.

What is the verified answer to “Solve this Time and Work question: Isha can finish a project in 20 days and Naina in 30 days. After working together for 5 days, Isha leaves. How many additional days will Naina require?”?

17.5 days, option C.

Which method solves this Time and Work item?

Rebuild and verify the complete work-rate equation.

Why are the other options incorrect?

18.5 days, 19.5 days, 16.5 days break a clue, direction, transition or operation.

How should the answer be checked?

Replay the rule from the first clue or term and test every intermediate step.

What is Time and Work and what is the basic concept?

Time and Work problems involve finding how long it takes to complete a task. Basic concept: If A can do a work in n days, A's one day work = 1/n. If A and B together can do work in n days, combined one day work = 1/n. Key formula: Total Work = Efficiency x Time. Time and Work is a major topic in SSC CGL, IBPS Bank PO, SBI PO, CAT, and Railway exams.

How to solve Time and Work problems using LCM method?

LCM Method: Assume total work = LCM of given days. Calculate each person's work per day = Total work divided by Days. Combined work per day = Sum of individual work rates. Time = Total work divided by Combined rate. Example: A can do work in 10 days, B in 15 days. LCM(10,15) = 30 units. A's daily work = 3 units, B's = 2 units. Together = 5 units/day. Time = 30/5 = 6 days. This avoids fractions and is much faster.