Solve this Time and Work question: Vikas can finish a project in 24 days and Lokesh in 36 days. After working together for 6 days, Vikas leaves. How many additional days will Lokesh require?
Last Updated:
This bilingual Time and Work item asks the learner to solve “Solve this Time and Work question: Vikas can finish a project in 24 days and Lokesh in 36 days. After working together for 6 days, Vikas leaves. How many additional days will Lokesh require?” through a complete, auditable work-rate equation. The validated answer is 21 days. The explanation preserves the original question-specific working, reconstructs the governing rule, checks every relevant condition or transition, and compares all three distractors. It builds disciplined reasoning, accurate option elimination and exam-ready verification for SSC, Railway, Banking, Defence, State examinations and other competitive tests.