Time and Work Questions and Answers – Page 8

Time and Work is a high-scoring and frequently asked topic in Quantitative Aptitude for competitive exams such as SSC CGL, SSC CHSL, IBPS PO, IBPS Clerk, SBI PO, SBI Clerk, RRB NTPC, and other banking and government job examinations. This topic deals with calculating how long it takes one or more people or machines to complete a given task, based on their individual work rates or efficiencies. The basic concept is that if a person can complete a piece of work in n days, their one-day work equals 1/n, and when multiple people work together, their combined one-day work is the sum of their individual one-day work rates. A strong understanding of time and work concepts is important because this topic is closely related to Time, Speed and Distance and Pipes and Cisterns problems. This topic page offers a detailed collection of time and work questions with step-by-step solutions designed to help aspirants build both speed and accuracy. The practice questions cover important variations such as work and efficiency problems, men-days-hours calculations, alternate day work patterns, work sharing and wages problems, and pipes and cisterns questions that use the same underlying concepts. Each question includes a clear explanation along with the LCM method and efficiency-based shortcut tricks that make solving time and work problems significantly faster during the exam. Aspirants preparing for SSC, banking, and railway exams often find time and work questions difficult when multiple people or machines with different efficiencies are involved, or when work is left incomplete and needs to be completed by another group. Our practice set addresses these challenges through clear worked examples, the LCM shortcut method for assuming total work, and formula-based approaches for combined work rates. Regular practice with these questions will strengthen your overall Quantitative Aptitude preparation and help you solve work and efficiency problems more confidently. Whether you are a beginner starting your exam preparation or an experienced aspirant sharpening your speed, this time and work question bank is designed to support learners at every level. Practice consistently, apply the shortcut methods provided, and use them to solve time and work questions accurately and quickly in your upcoming SSC, banking, railway, and other competitive government examinations.

Exams Covered:

SSC CGL
SSC CHSL
SSC MTS
IBPS PO
IBPS Clerk
RRB NTPC
UPSC
State Exams
& More

Solve this Time and Work question: Yash can do a job in 20 days and Dev in 30 days. They work on alternate days, beginning with Yash. What percentage of the job is completed in 14 days?

Solve this Time and Work question: Priya can do a job in 16 days and Tanvi in 24 days. They work on alternate days, beginning with Priya. What percentage of the job is completed in 12 days?

Solve this Time and Work question: Neeraj can do a job in 15 days and Sahil in 20 days. They work on alternate days, beginning with Neeraj. What percentage of the job is completed in 10 days?

Solve this Time and Work question: Harish can do a job in 12 days and Jatin in 18 days. They work on alternate days, beginning with Harish. What percentage of the job is completed in 8 days?

Solve this Time and Work question: Aarti can do a job in 10 days and Kusum in 15 days. They work on alternate days, beginning with Aarti. What percentage of the job is completed in 6 days?

Solve this Time and Work question: Lokesh is 80% more efficient than Vikas. If Vikas takes 45 days to complete a contract, how many days will Lokesh take?

Solve this Time and Work question: Naina is 60% more efficient than Isha. If Isha takes 40 days to complete a contract, how many days will Naina take?

Solve this Time and Work question: Tarun is 50% more efficient than Manoj. If Manoj takes 36 days to complete a contract, how many days will Tarun take?

Solve this Time and Work question: Seema is 25% more efficient than Geeta. If Geeta takes 30 days to complete a contract, how many days will Seema take?

Solve this Time and Work question: Kabir is 20% more efficient than Farhan. If Farhan takes 24 days to complete a contract, how many days will Kabir take?

FAQ

Time & Work FAQs

Common questions and clear answers for this topic.

What is Time and Work and what is the basic concept?

Time and Work problems involve finding how long it takes to complete a task. Basic concept: If A can do a work in n days, A's one day work = 1/n. If A and B together can do work in n days, combined one day work = 1/n. Key formula: Total Work = Efficiency x Time. Time and Work is a major topic in SSC CGL, IBPS Bank PO, SBI PO, CAT, and Railway exams.

How to solve Time and Work problems using LCM method?

LCM Method: Assume total work = LCM of given days. Calculate each person's work per day = Total work divided by Days. Combined work per day = Sum of individual work rates. Time = Total work divided by Combined rate. Example: A can do work in 10 days, B in 15 days. LCM(10,15) = 30 units. A's daily work = 3 units, B's = 2 units. Together = 5 units/day. Time = 30/5 = 6 days. This avoids fractions and is much faster.

How to solve problems when people join or leave work midway?

When worker joins midway: Find work done before and after they join. If A works for x days and B joins for y days, Total work = A's work in x days + (A+B)'s work in y days. Example: A alone in 20 days. If A works 6 days then B joins, to find when work completes: A's 6 days work = 6/20 = 3/10. Remaining = 7/10. If A+B together rate = 1/12, days to finish = (7/10)/(1/12) = 8.4 days.

What are Pipes and Cistern problems in Time and Work?

Pipes and Cistern: Inlet pipe fills cistern (positive), Outlet pipe empties cistern (negative). If inlet fills in x hours, rate = 1/x per hour. If outlet empties in y hours, rate = 1/y per hour. Net rate = 1/x - 1/y. Time to fill = xy/(y-x) hours if y > x. Cistern fills if net rate is positive. These problems are standard in IBPS, SBI, and SSC competitive exams.

What is work equivalence and efficiency in Time and Work problems?

Work Equivalence: Men x Days = Women x Days (when efficiency ratio is known). If 1 man = 2 women in efficiency, then 10 men = 20 women. Men-Days concept: 10 men x 5 days = 50 man-days. If 8 men do same work, days = 50/8 = 6.25 days. For wages: divide total payment in ratio of work done. If A and B complete work together and A worked fewer days, calculate individual shares accordingly.

What is the verified answer to “Solve this Time and Work question: Yash can do a job in 20 days and Dev in 30 days. They work on alternate days, beginning with Yash. What percentage of the job is completed in 14 days?”?

58.33 %, option D.

Which method solves this Time and Work item?

Rebuild and verify the complete work-rate equation.

Why are the other options incorrect?

59.33 %, 60.33 %, 56.33 % break a clue, direction, transition or operation.

How should the answer be checked?

Replay the rule from the first clue or term and test every intermediate step.

What is the verified answer to “Solve this Time and Work question: Priya can do a job in 16 days and Tanvi in 24 days. They work on alternate days, beginning with Priya. What percentage of the job is completed in 12 days?”?

62.5 %, option C.

What is the verified answer to “Solve this Time and Work question: Neeraj can do a job in 15 days and Sahil in 20 days. They work on alternate days, beginning with Neeraj. What percentage of the job is completed in 10 days?”?

58.33 %, option B.

What is the verified answer to “Solve this Time and Work question: Harish can do a job in 12 days and Jatin in 18 days. They work on alternate days, beginning with Harish. What percentage of the job is completed in 8 days?”?

55.56 %, option A.

What is the verified answer to “Solve this Time and Work question: Aarti can do a job in 10 days and Kusum in 15 days. They work on alternate days, beginning with Aarti. What percentage of the job is completed in 6 days?”?

50 %, option D.

What is the verified answer to “Solve this Time and Work question: Lokesh is 80% more efficient than Vikas. If Vikas takes 45 days to complete a contract, how many days will Lokesh take?”?

25 days, option C.

What is the verified answer to “Solve this Time and Work question: Naina is 60% more efficient than Isha. If Isha takes 40 days to complete a contract, how many days will Naina take?”?

25 days, option B.

What is the verified answer to “Solve this Time and Work question: Tarun is 50% more efficient than Manoj. If Manoj takes 36 days to complete a contract, how many days will Tarun take?”?

24 days, option A.

What is the verified answer to “Solve this Time and Work question: Seema is 25% more efficient than Geeta. If Geeta takes 30 days to complete a contract, how many days will Seema take?”?

24 days, option D.

What is the verified answer to “Solve this Time and Work question: Kabir is 20% more efficient than Farhan. If Farhan takes 24 days to complete a contract, how many days will Kabir take?”?

20 days, option C.

Related Practice

Parent category aur related practice pages se apni preparation continue karein.

Similar Topics

Practice related topics from the same category.

Top 5 Topics

Open high-value topics for stronger internal linking.

Top 5 Categories

Explore popular categories for more exam practice.

Top Time and Work in Quantitative Aptitude Questions – Page 8 | Exambodh